Question 1 - Qid 6113151, Risk Management, 2. Process, 11.7 Monitor Risks
The project management plan specifies that a predictive development approach has been selected to produce the project deliverables.
Where in the project life cycle will the overall project risk be the lowest?
A. Starting the project
B. Organizing and preparing
C. Carrying out the work
D. Closing the project