Works on the first project under the state's highly ambitious Penang Transport Master Plan (PTMP) — the Tun Dr Lim Chong Eu Expressway - Air Itam bypass — have started and achieved eight per cent progress.
The 6km bypass, to be built at a cost of RM851 million, is expected to be completed in 2025.
Among the distinctive features of the underpass are that some parts will be elevated and it will have three short-distance twin land tunnels.
Visiting the project site this morning, Chief Minister Chow Kon Yeow said he was happy to note that the project had achieved eight per cent progress, two per cent ahead of the targetted six per cent progress.