The plumbers glued on test caps, and I used a pump and tank in the back of my truck to fill the entire system with water for inspection.
We filled this 10' tall pipe all the way to the top with water.
Here’s the layout: this two-inch electrical conduit goes from the sub-panel to the main service.
Then a floor drain for the water heater, and the ¾” water line that comes in from the outside of the building.
Next a vent pipe for the floor drain.
This is the stub up for the toilet for the first bathroom, sink drain, toilet for second bathroom, floor drain for the HVAC system, another vent for the drain, and the second bathroom sink and the kitchenette sink drain.
Here’s where we branched off with a 2” line for the mop sink, then there’s a drain for the high and low water fountains.
Finally, through the foundation sleeve to the outside. @hausplans