Track Installation and Road Widening on Hurontario Street between Park Street and the QEW
July 2024 to June 2025
What work is taking place?
As construction on the Hazel McCallion Line Light Rail Transit progresses, communities in Mississauga South can expect the following construction activities in the coming months:
* The removal of hydro and telecommunication poles along the west side of Hurontario Street and the connection of new Alectra services to adjacent properties
* Grading changes to the adjacent boulevard and driveways to match the road elevations,
* Road widening activities on both sides of Hurontatio Street, to accommodate the construction of the guideway in the centre of the roadway later this year, and the construction of new sidewalks along the west side of the street and improvements to the multi-use pathway on the east side of the street. The guideway and tracks will be constructed through the Mineola intersection this summer along with the start of construction of the stop at Mineola.
* The installation of architectural finishes at Port Credit Station
* The completion of the flood walls at Mary Fix Creek
* The opening of a new east/west connection across Hurontario Street with a new signalized intersection at Eaglewood Boulevard; and
* The addition of new lanes for northbound traffic at the new QEW underpass
Most work is scheduled from Monday to Saturday from 7 a.m. to 7 p.m. and will take place within the staged area separated by traffic barrels and temporary fencing. Temporary closures of roadways at intersections will be required to ensure that crews onsite are able to safely complete the work. Some overnight and weekend work may also be required. Additional notification will be provided when there is a requirement for a temporary road closure, overnight, or Sunday work. We will also communicate with individual property owners concerning potential property access requirements such as utility connections and temporary driveway closures for final restoration and boulevard grading. Additional signage will also be placed to inform motorists and pedestrians about any sidewalk closures or changes to traffic configuration.
As construction staging moves to the centre of the roadway for guideway, track, and LRT stop construction, we remind the motorists that permanent turning restrictions will be implemented to ensure the safe flow of traffic. This means that left turns will be restricted to signalized intersections. Entering and exiting properties along Hurontario Street will require motorists to make right turns.
TIMING
• Work could be rescheduled and delayed due to weather conditions or unforeseen circumstances
• Visit www.miway.ca/updates for updates on your bus route.
TRAFFIC DETAILS
* Temporary lane reductions will be required on Hurontario Street.
* Traffic delays are expected.
* Watch for slow moving vehicles entering and exiting work areas.
* Remember to reduce your speed when approaching lane reductions.
PEDESTRIAN DETAILS
* Please take care when travelling near construction areas.
* Sidewalk access in the area could be affected.
* Watch for additional signs directing pedestrians as detours may be required.
* Clear and defined walking paths will be maintained during construction to ensure pedestrian safety.
WHAT TO EXPECT?
* Every effort will be made to minimize disruptions.
* Residents and businesses near the work site can expect to hear noise and vibration caused by trucks, excavators, loaders, triaxles, backhoes, and other construction equipment related to this work.
PROPERTY DETAILS
* Please ensure any personal belongings, such as signs, benches and underground sprinklers on city owned land have been relocated prior to the beginning of construction.
* For details on your property boundaries, please refer to your land survey, or consult an Ontario Land Surveyor.
TRANSIT DETAILS
* MiWay will continue to operate with regular service.
* Watch for additional signs directing passengers at bus stops as boarding areas may be relocated.
CONTACT US
• Metrolinx has a dedicated community engagement team to work with residents and can be reached through a 24-hour line416-202-7500
Contact Us:
Call us: 416-202-7500
Write to us at: peel@metrolinx.com
Find us on X @HMcCallionline
Visit the website and sign up for our newsletter: www.metrolinx.com/hazelmccallionline