1.)SANCTION OF WORK
Reconnaissance Engineering cum Traffic Survey for a new BG line between Bellary and Lingsugur was sanctioned vide Blue Book No 22 of 2014-15.
2.)INTRODUCTION
The project area is in Karnataka state and falls within the jurisdiction of Hubli Division of South Western Railway. Bellary Junction (BAY) is a major Junction station connecting to Guntakal (GTL), Hubli (UBL) and Chikjajur (JRU). Lingasugur, which is currently not connected by rail, is a proposed junction station for this project. Bagalkot (BGK), on the Gadag (GDG South Western Railway) Solapur (SUR Central Railway) line is the nearest railway station to Lingasugur and is situated at a distance of about 100 km by road.
3.)FOREST AREA
There is no forest area in the proposed alignment.
4.)DISCUSSION OF ROUTE
The proposed alignment takes off at Bellary Cantonment, an existing halt station on the BAY-HPT section, situated at a chainage of 5.05 km from Bellary Junction. It connects the prominent towns in the region namely, Siruguppa, Sindhanur and Maski. The alignment is 132.18 km in length with a total curve length of 38.52 km (28.14%). It also has 95 road crossings (ROB-18, RUB77) and 23 major bridges.
5.)CONCLUSION
At an estimated project cost of Rs. 1161.95 Crores, the cost per km is estimated to be Rs. 8.80 Crores.
Bellary September 23: Bellary MP Y Devendrappa has appealed to the central government in the Parliament session to provide the necessary funds announced in the Union Budget 2014-15 for the commencement of the new railway line between Bellary-Shiraguppa- Lingasur.
vai Devendrapra raised the matter today in the zero hour of Parliament. In the budget of 2014-15, the launch of the new railway line was announced. An estimate of Rs 1160 crore in this regard was submitted to the Railway Board in January 2019.
But in the backdrop of not announcing any grant for this in the budget of 2019-20, it has fallen into a quagmire in the Railway Board itself. Construction of Bellary - Shiraguppa - Sindhanur - Lingasur railway line will connect Wadi, Solapur, North India, North East India and Kalyan to Karnataka. Therefore, he requested to give financial grant for this work and enable him to start the work.
#Ballary lingasuru new railway line
#new railway projects in karnataka
South western railway
#Kannada Swaroopa
#Sindhanur railway station
#sindhanur railway station construction
#train sindhanur
#southwestern railway
#Asset Kannada
Ballari new railway line
#Lingasugur new railway line
#Ballari to Lingasugur train
#Ballari siraguppa Lingasur railway line
#Ballari siraguppa Lingasur railway project
#bellary
#Ballari siraguppa Lingasur railway project
#New railway project
Gadag Wadi new railway line
Link:- [ Ссылка ]
Highest priority train in Indian railways
Link:-[ Ссылка ]
credit for some video clips images and music:-
pixels
audio library
Google images
Disclaimer :- Video is for educational purpose only. Copyright Disclaimer Under Section 107 of the Copyright Act 1976, allowance is made for "fair use" for purposes such as criticism will, comment, news reporting, teaching, scholarship and research. Fair use is a use permitted by copyright statue that might otherwise be infringing. -This video has no negative impact on the original works (It would actually be positive for them) -This video is also for teaching purposes. -It is not transformative in nature. -I only used bits and pieces of videos to get the point across where necessary.
Like, Share & SubscribeBallary new railway line
Ballary to Lingasugur
Ballary to Lingasugur train
Ещё видео!