CAVITE-LAGUNA EXPRESSWAY (CALAX) PROJECT
Project Description:
The project is a 44.58 km. four (4)-lane closed-system tolled expressway connecting CAVITEX and SLEX. The project will start from the CAVITEX in Kawit, Cavite and end at the SLEX-Mamplasan Interchange in Biñan, Laguna. The project will have the following subsections:
Project Subsections
Length
(km)
1
Cavitex Connection to Open Canal Interchange
8.68
2
Open Canal Interchange to Governor’s Drive Interchange
9.86
3
Governor’s Drive Interchange to Silang (Aguinaldo) Interchange
8.64
4
Silang (Aguinaldo) Interchange to Silang East Interchange
3.16
5
Silang East Interchange to Sta. Rosa-Tagaytay Interchange
5.14
6
Sta. Rosa-Tagaytay Interchange to Laguna Boulevard Interchange
2.34
7
Laguna Boulevard Interchange to Laguna Technopark Interchange
3.30
8
Laguna Technopark Interchange to Mamplasan Toll Barrier
3.46
PPP Scheme: Solicited Project, Build-Transfer-Operate
-Private sector to finance, construct, operate and maintain the entire expressway
Concession Period: 35 years (including 5 years design and construction)
Start of Concession Period: July 10, 2015 (TCA Signing Date)
Right of Way:
60 meters, except for Laguna Techno Park & Laguna Boulevard (40 meters), and Greenfield Development Corporation (50 meters).
Interchanges:
8 interchanges and 1 toll barrierr
Bridges:
3,575 meters inclusive of 444 meters of viaduct
Project Objectives:
This project aims to:
Support national development policy and provide efficient transport facilities for the Eco-zones in Cavite and Laguna.
Reduce traffic congestion particularly in Governor’s Drive, Aguinaldo Highway and Sta. Rosa-Tagaytay Road which are heavily congested.
Improve competitiveness of Region IV-A/CALABARZON as an investment destination.
Project Benefits:
At the end of construction, the project is expected to:
Reduce travel time from CAVITEX (Kawit) to SLEX (Mamplasan Interchange in Biñan, Laguna) from 2 hours to 35 minutes (70% reduction).
Project Concessionaire:
MPCALA Holdings Inc.
Project Cost:
Activities
Amount (Billion)
Civil Works
P 25.425
Right-of-Way
P 10.201
Independent Consultant (50%)
P 0.112
Total
P 35.738
Project Status:
· Right-of-Way Acquisition (ROWA) accomplishment (actual site possession)
Ø Laguna Side : 100.00%
Ø Cavite Side : 74.40%
· Subsections 8, 7 and 6 (Sta. Rosa to Mamplasan) were partially opened to traffic on October 30, 2019.
· Toll Operation Permit (TOP) was issued last February 7, 2020 for Subsections 8, 7 and 6.
· Toll Operation Permit (TOP) was issued last June 18, 2021 for Subsection 5.
· Subsection 5 (Sta. Rosa to Silang East IC) was open to traffic last August 24, 2021.
· Contractor for Cavite Segment Subsection 1 already mobilized.
· Interim Permit to Operate was issued last November 6, 2023 for Subsection 4.
· Subsection 4 (Silang East IC to Silang Aguinaldo IC) was open to traffic last November 8, 2023.
· Toll Operation Permit (TOP) was issued last January 22, 2024 for Subsection 4.
Project Alignment:

Project Timeline:
Segment
Start Date
Completion Date
Remarks
Laguna Segment
100.00%
Subsection 8
July 2017
October 2019
100%
Subsection 7
July 2017
October 2019
100%
Subsection 6
September 2018
October 2019
100%
Subsection 5
September 2018
August 2021
100%
Subsection 4
March 2021
December 2023
100.00%
Cavite Segment
12.59%
Subsection 3
July 2019
December 2024
7.90%
Subsection 2
July 2019
June 2025
11.32%
Subsection 1
July 2019
May 2025
17.05%
Overall accomplishment: 60.00%