This update covers construction work through February 3, 2018. Crews in this segment have taken down most of the properties in the right of way, constructed the 40th Street bridge, constructed box culverts, closed Pecos Road west of 17th Avenue and widened Loop 202 Eastbound lanes. Over the next month, crews will continue constructing the 17th and 24th Street bridge, build a dirt embankment west of 32nd Street, widen 40th Street, relocate utilities, move the well water near 24th Street, blasting west of Desert Foothills Parkway, and work on building up the 20 foot sound wall. City of Phoenix crews will also install a 48 inch waterline at 32nd Street.
Remember to slow down and drive safely in construction zones!