How to Terminate a 25 Pair 1A4 Distribution Connector
Materials Required:
PTBX-16A-BL: Impact Termination Tool
MST-502: Cable Prep Tool
TMBX-1A4: 25 Pair 1A4 Distribution Connector (4 Pair Markings)
MST-501B: Cable Prep Tool
TMBX-4POSN: 100 Pair Distribution Frame
TF-4IV: 4" Nylon Cable Ties
TMBX-DSWH-EA: Designation Strip (White)
TMBX-DLBL-EA: Designation Label (Blue)
FT4-4PC5EBLSL2: 4 Pair CAT 5E UTP Solid Cable (Blue)
Step 1:
Cut the specified length of 4 Pair CAT 5E UTP Solid Cable (FT4-4PC5EBLSL2) and insert into the Cable Prep Tool (MST-501B). Rotate in one direction 1-2 turns.
Step 2:
The UTP Cable will be scored. Remove the jacket exposing the 8 insulated conductors and a nylon thread pull string. Use the pull string to strip the jacket a further 6 inches.
Step 3:
Place Nylon Cable Ties into the designated slots of the 25 Pair 1A4 Distribution Connector (TMBX-1A4). Place the exposed UTP Cables along the top of the Distribution Connector with the 4 pair markings starting from the left side and secure the Cable Ties.
Step 4:
Install the Distribution Connector into the required position of the 100 Pair Distribution Frame (TMBX-4POSN). Separate each pair of the UTP Cable and lace into the Distribution Connector according to the required wiring code. Use the Impact Termination Tool (PTBX-16A-BL) to punch down and cut one insulated conductor at a time.
Step 5:
Remove the Distribution Connector to inspect that all insulated conductors are terminated to the (IDC) Insulated Displacement Connectors. Insert the Distribution Connector into the Distribution Frame with the terminated Cable side down.
Step 6:
Place the required Designation Label (TMBX-DLBL-EA) onto the Designation Strip (TMBX-DSWH-EA) and install into the appropriate position of the Distribution Frame.